Project Spotlight

Chicago Breaks Ground on $917 Million O’Hare Concourse E

KEY POINTS  

  • Chicago broke ground Nov. 17 on a $917 million, 24-gate concourse at O’Hare International Airport.

  • The $640 million first phase includes 14 gates and about 315,000 square feet, with completion targeted for 2030.

  • A $277 million second phase will add 10 gates, with the full concourse expected in 2034.

Chicago broke ground on The New Concourse E according to its Nov. 17 announcement. The project is a $917 million, 24-gate expansion at O’Hare International Airport, launching the next major phase of the airport’s ORDNext modernization program. 

Concourse E, developers said, is designed for regional, narrow-body aircraft, and is expected to enhance connectivity for domestic and select international flights.

Screenshot 2026-11-23 133831

A rendering of The New Concourse E at O’Hare International Airport. Chicago broke ground Nov. 17 on the $917 million, 24-gate expansion launching the next major phase of the airport’s ORDNext modernization program. Image: ORDNext

The first phase of The New Concourse E, budgeted at $640 million, includes:

  • 14 domestic-capable gates

  • 315,000 square feet of new passenger space

  • Nearly 21,000 square feet of concession space and a public art program

The two-level concourse will extend more than 1,000 feet and will be accessed primarily through an underground passenger tunnel connecting it to The New Concourse D.

The $1.4 billion New Concourse D is scheduled for completion in late 2028.

Econ Ads_Banners4-1

 

ORDNext is a major expansion and modernization of Chicago O’Hare International Airport. Developers said The New Concourse D, The New Concourse E and the O’Hare Global Terminal represent the "centerpiece of ORDNext, the largest terminal expansion in O’Hare’s history."

The project, once completed, is expected to increase O’Hare’s gate capacity by approximately 14%.

ordnext-head

A rendering is shown in the above image of Chicago O’Hare International Airport, where construction to modernize and upgrade began in August 2025. The 19-gate New Concourse D is under construction and scheduled for completion in late 2028. The O’Hare Global Terminal is scheduled to open in 2033, and the broader program is expected to be complete in 2034. Image: ORDNext

A second phase of Concourse E will add 10 gates for $277 million after completion of the O’Hare Global Terminal, bringing the concourse to its full 24-gate configuration in 2034. 

The AECOM Hunt Clayco Bowa joint venture is leading construction. Skidmore, Owings & Merrill is designing the concourse with Ross Barney Architects, Juan Gabriel Moreno Architects and Arup.

The city said the phases will be sequenced with other airport work, including the Global Terminal.

Stay Connected

Stay connected with ConstructConnect News for construction industry news and construction market analysis to stay ahead of what’s building next.

About ConstructConnect

At ConstructConnect, our software solutions provide the information construction professionals need to start every project on a solid foundation. For more than 100 years, our insights and market intelligence have empowered commercial firms, manufacturers, trade contractors, and architects to make data-driven decisions and maximize productivity.

ConstructConnect is a business unit of Roper Technologies (Nasdaq: ROP), part of the Nasdaq 100, S&P 500, and Fortune 1000.

For more information, visit constructconnect.com

Marshall Benveniste
As Managing Editor of ConstructConnect News and Senior Content Marketing Manager with ConstructConnect’s Economics Group, Marshall Benveniste brings construction-sector insight and economic perspective to every article. He leads coverage of U.S. nonresidential construction and the broader construction economy, translating complex data and market movements into practical narratives for industry professionals. Before joining ConstructConnect in 2021, Marshall spent 15 years shaping marketing communications for financial services and specialty construction firms, giving him a front-row view of how capital, risk, and project delivery intersect in the built environment. His Ph.D. in Organizational Management and MBA further inform his work, grounding his reporting in how companies and project teams make sound decisions.